Abstract. Based on data from bauxite production in April 2019 at PT. Bhakti Karya Mandiri, bauxite
production did not reach the target. the production target is 25000 bcm. but the production achieved was
only 16,916 bcm. This is caused by wasted work time and disruption time which causes operating time
and productivity to be low. To determine the potential for improving the production process and the
effectiveness of using equipment, an analysis using the overall shipping effectiveness (OEE) method
needs to be done. After analysis and improvement methods were carried out, the production of Kobelco
SK 330 exceeded the planned target which was previously 16,916 bcm to 25,629 m³. But the OEE value
is still <61% not yet achieved the world class OEE> 85%, it can be concluded that the use of equipment
is not optimal. Better to make improvements to reduce wasted working hours

Keywords: Bauxite Mining, Overall Shipping Effectiveness (OEE) Method, Production, Excavator, and Dump Truck