Perencanaan Fleet Menggunakan Metode Monte Carlo dengan Pendekatan Cycle Time di PT. ANTAM Tbk, UBP Bauksit Tayan, Kalimantan Barat

Resi Hutriayu(1), Adree Octova(2),
(1) Universitas Negeri Padang  Indonesia
(2) Universitas Negeri Padang  Indonesia

Corresponding Author


DOI : https://doi.org/10.24036/bt.v5i2.107826

Full Text:    Language : en

Abstract


Abstract. PT. ANTAM Tbk. UBPB Tayan, West Kalimantan conducts exploration and exploitation of metal minerals in the Tayan Hilir, West Kalimantan. PT. ANTAM Tbk. UBPB Tayan is a bauxite mining which is one of the operational activities originating from the washing crude bauxite (CBx) from mining activities to produce wash bauxite (WBx) by doing two activities in the process of transporting material to washing plant area. PT. ANTAM Tbk. UBPB Tayan undertake mining activities at front of Bukit 7B with a production target of 3.175.000 wmt in the production target WBx the planned CBx mining production is 6,487,242 wmt in 2019. Based on field observations, the production target in Bukit 7B area PT. ANTAM Tbk. UBPB Tayan has still not been reached, and the actual fleet used today is inadequate to achieve the next month's production target. Efforts to produce not achieving production targets by planning using the Monte carlo method with a time cycle approach. Related to production targets and the number of tools that will be used by the company in fleet planning, work composition, effectiveness, and compatibility of the tools in the two work plans are able to minimize the achievement of production targets. Where the probability value of 50% and 100%.

Keywords: Crude Bauxite, Production, Fleet, Cycle Time anda The Monte Carlo Method


Article Metrics

 Abstract Views : 461 times
 PDF Downloaded : 218 times

Refbacks

  • There are currently no refbacks.